Date: 2016-10-31
Client: C & E ENGINEERING – CRUSHER REPAIRS & SPARES
Skills: ACAD 2017 and Solidworks, Auto cad 2015 & SolidWorks 2016
Period Employed (start and finish) JUNE 2016 – OCTOBER 2016
Position: Draughtsman
List Projects:
Projects 1: Not a project company.
Duties and Responsibilities: Modelling crushers and related parts to create drawings from them.
List Projects:
Projects: Not a project company.
Duties and Responsibilities: Reverse engineering of crushers and related spares.
Date: 2015-06-30
Client: Victor Soap Industries – Soap Manufacturing
Skills: Autocad 2017
Period Employed (start and finish) March 2015 till June 2015
Position: Project coordinator/Layout draughtsman
Projects: Not a project company.
Duties and Responsibilities: 3D Modelling,Layouts of new plant & equipment.
Date: 2015-02-28
Client: WorleyParsons – Mining
Skills: Autocad 2010 & 2013
Period Employed (start and finish) June 2014 till February 2015
Position: Layout draughtsman
List Projects:
Projects 1: Wafi Golpu prefeasibility study.
Duties and Responsibilities: Layouts of mine surface infrastructure & equipment.
Projects 2: Twickenham Hackney platinum mine.
Duties and Responsibilities: Detailing and backdraughting of conveyors.
Projects 3: Exxaro Matla mine 1 relocation project.
Duties and Responsibilities: Layout, detailing and backdraughting of conveyors.
Date: 2014-06-17
Client: SCAW METALS – MINING. CAST PRODUCTS FOR MINING & RAILWAYS
Skills: ACAD 2010
Period Employed (start and finish) 25TH JULY TILL 17 JUNE 2014
Position: Draughtsman
Projects 1: Ghana roll former project. (New ball plant) Grinding media.
Duties and Responsibilities: Compiling data packs for procurement department in order to establish a budget total for feasibility.
Date: 2013-07-31
Client: DRA – Mining
Skills: Autocad 2010 & 2013. Navisworks
Period Employed (start and finish) August 2010 till July 2013
Position: Layout draughtsman
List Projects:
Projects 1: Moatize coal washing plant – draughtsman
Duties and Responsibilities: Layouts & detailing of screens, tanks and coal washing equipment.
Projects 2: Dargues Gold reef project Australia – draughtsman
Duties and Responsibilities: Layout of gold plant. Existing gold plant had to be re-located and all existing equipment had to be re-used. Original plant was done in Autocad 3D in Australia.
Projects 3: Boss Mining – Kakanda Copper project Zaire
Duties and Responsibilities: Layouts and detailing of new surface plant equipment for new copper concentrator.
Projects 4: Northam – Booysendal platinum mines – new concentrator
Duties and Responsibilities: Layouts and detailing of new surface plant equipment for new platinum concentrator.
Projects 5: Zimplats – Zimbabwe Platinum Mines LTD.Ngezi Expansion Project.
Duties and Responsibilities: Layouts and detailing of conveyors and drives.
Projects 6: ZWBJV PROJECT 1 – Maseve
Duties and Responsibilities: Layouts and detailing of apron feeder and apron feeder chutes.
Date: 2010-08-31
Client: ELB – Mining
Skills: ACAD 2010
Period Employed (start and finish) May 2010 – August 2010
Position: Draughtsman
List Projects:
Projects 1: VALE COAL
Duties and Responsibilities: Layout new feed conveyor to coal washing plant.
Projects 2: Sierra Leoni
Duties and Responsibilities: Layouts for revamping disused train load-out station. Detailing new discharge bin and equipment.
Projects 3: KHUMANI IRON ORE
Duties and Responsibilities: Layout and detail emergency overflow chute.
Date: 2010-05-31
Client: SENET – MINING
Skills: Autocad 2010
Period Employed (start and finish) JULY 2009 – MAY 2010
Position: Draughtsman
List Projects:
Projects 1: Iron ore processing plant – MALI
Duties and Responsibilities: Detailing all surface plant equipment from conveyors, bins, tanks, chutes, apron feeder bins etc.
Date: 2009-07-31
Client: RSV KENYUKA – MINING
Skills: Auto cad 2010
Period Employed (start and finish) OCTOBER 2008 – JULY 2009
Position: Draughtsman
List Projects:
Projects 1: PALESA & MBALI COAL WASHING PLANTS.
Duties and Responsibilities: Site measure disused coal washing plant in order to restore. New layouts had to be made showing new equipment. Original plant equipment and infrastructure was stripped and vandalised.
Projects 2: SPITZKOP PLATINUM CONCENTRATOR
Duties and Responsibilities: Layouts and detailing.
Date: 2009-07-31
Client: RSV KENYUKA – MINING
Skills: Auto cad 2010
Period Employed (start and finish) OCTOBER 2008 – JULY 2009
Position: Draughtsman
List Projects:
Projects 1: PALESA & MBALI COAL WASHING PLANTS.
Duties and Responsibilities: Site measure disused coal washing plant in order to restore. New layouts had to be made showing new equipment. Original plant equipment and infrastructure was stripped and vandalised.
Projects 2: SPITZKOP PLATINUM CONCENTRATOR
Duties and Responsibilities: Layouts and detailing.
Date: 2008-10-31
Client: SANDVIK – MINING – MATERIALS HANDLING
Skills: Auto cad 2010
Period Employed (start and finish) OCTOBER 2006 – OCTOBER 2008
Position: Draughtsman
List Projects:
Projects 1: Goedgevonden coal processing plant.
Duties and Responsibilities: Green fields project. Plant and conveyor layouts. Site visits. Detailing conveyors, chutes, bins, transfer buildings and all surface plant related equipment.
Projects 2: Ngezi Expansion Project
Duties and Responsibilities: Layout and detailing conveyors.
Projects 3: Barrick Sedibelo – Anglo Platinum
Duties and Responsibilities: Layout new proposed platinum mine.
Projects 4: Brakfontein UG2 STUDY
Duties and Responsibilities: Layout all headchutes to suit beltcon program.
Projects 5: DCP IN DRC – KOV OPEN PIT MINE
Duties and Responsibilities: Layout new conveyors in order to re-open mine.
Projects 6: AMANDELBULT
Duties and Responsibilities: Conveyor and related equipment detailing.
Date: 2006-10-31
Client: BATEMAN – MINING
Skills: Auto cad 2010
Period Employed (start and finish) FEBRUARY 2006 – OCTOBER 2006
Position: Draughtsman
List Projects:
Projects 1: Finch Diamond mine- Sorting plant upgrade.
Duties and Responsibilities: Detailing all diamond handling equipment from 3D layout and site visit.
Date: 2006-02-28
Client: ETS – MATERIALS HANDLING/MINING
Skills: Auto cad 2010
Period Employed (start and finish) OCTOBER 2005 – FEBRUARY 2006
Position: Draughtsman
List Projects:
Projects 1: Bogoso Gold Limited.
Duties and Responsibilities: Conveyor layout and detailing. Detailing chutes, bins and structures.
Date: 2005-10-31
Client: MDM FERROMAN
Skills: Auto cad 2010
Period Employed (start and finish) MARCH 2005 – OCTOBER 2005
Position: Draughtsman
List Projects:
Projects 1: Shisen iron ore – upgrade
Duties and Responsibilities: Conveyor layout and detailing. Detailing chutes, bins and structures.
Date: 2005-03-31
Client: C & E ENGINEERING – CRUSHER REPAIRS & SPARES
Skills: Auto cad 2007
Period Employed (start and finish) APRIL 2004 – MARCH 2005
Position: Draughtsman/Sales Representitive
List Projects:
Projects: Not a project company.
Duties and Responsibilities: Re organise the drawing office. Create drawing standards. Move all existing drawings onto proper drawing sheets. Create drawing data base and filing system. Reverse engineering of crushers and related spares. Was made part of the sales team and given specific sales region.
Date: 2004-03-31
Client: DELKOR TECHNIK – MINING PROCESS EQUIPMENT (DEWATERING)
Skills: Auto cad 2007, Pro Engineer
Period Employed (start and finish) MARCH 2001 – MARCH 2004
Position: Draughtsman
List Projects:
Projects: South Deep, Rossing Uranium and many others.
Duties and Responsibilities: Layout and detailing filter presses, thickeners and belt filters.
Date: 2001-03-31
Client: JCI – MINING HOUSE
Skills: Micro GDS
Period Employed (start and finish) DECEMBER 2000 – MARCH 2001
Position: Draughtsman
List Projects:
Projects: South Deep Mine – Greenfields project.
Date: 2000-12-31
Client: EVERITE – ASBESTOS SHEETING MANUFACTURER
Skills: Auto cad 2007
Period Employed (start and finish) APRIL 2000 – DECEMBER 2000
Position: Draughtsman
List Projects:
Projects: Relocation of Belville plant to Klipriver site.
Duties and Responsibilities: Layout factory plant and equipment to suit site. Detail new process tanks and equipment.
Date: 2000-04-30
Client: ARMINCO – PAPER AND PULP PROCESS EQUIPMENT
Skills: Auto cad 2007
Period Employed (start and finish) JANUARY 2000 – APRIL 2000
Position: Draughtsman
List Projects:
Projects: SAPPI Springs upgrade.
Duties and Responsibilities: Site measure old vats and paper/pulp equipment and produce working/manufacturing drawings.
Date: 1999-12-31
Client: W.G. DAVEY / DAVEY INDUSTRIAL – MATERIALS HANDLING EQUIPMENT
Skills: Auto cad 2007
Period Employed (start and finish) OCTOBER 1998 – DECEMBER 1999
Position: Project Engineer/Draughtsman
List Projects:
Projects: BIG BEND SUGAR MILL SWAZILAND, SAB, ABBATOIRS BOTSWANA
Duties and Responsibilities: Site inspect/measure. Proposal drawings, detail drawings of screw conveyors, bucket elevators, ribbon blenders, slide gates and related equipment. Oversee installation and commissioning.
Date: 1998-09-30
Client: JOY MINING MACHINERY (P&H HARNISCHFEGER) – COAL MINING
Skills: Auto cad 2007
Period Employed (start and finish) NOVEMBER 1994 – SEPTEMBER 1998
Position: Chief Draughtsman Longwall Section.
List Projects:
Projects: Various for different coal mines such as New Denmark, Matla, Arnot, Twistdraai, and Kleikoppie collieries.
Duties and Responsibilities: Responsible for integrating Longwall drawings into Joy system and onto SAP system. Involved in all new designs of Longwall equipment. Travelled to Joy UK offices and plants to aid in merger between Joy Mining and Long wall International.
Date: 1994-10-31
Client: LONGWALL INTERNATIONAL
Skills: Auto cad 9, 2007
Period Employed (start and finish) JANUARY 1991 – OCTOBER 1994
Position: Draughtsman / Chief Draughtsman
List Projects:
Projects: Various for different coal mines such as New Denmark, Matla, Arnot, Twistdraai, and Kleikoppie collieries.
Duties and Responsibilities: Layout and detailing long wall mining equipment such as line pans, roof supports, and in-buy and out-buy units, stage loaders and power packs. Many site visits under taken to measure up equipment and witness wear conditions. Was promoted to chief draughtsman.
Date: 1991-01-31
Client: EFCO FURNACES
Skills: Drawing board
Period Employed (start and finish) NOVEMBER 1990 – JANUARY 1991
Position: Draughtsman
List Projects:
Projects: SA MINT
Duties and Responsibilities: Layout and detailing of mesh belt furnaces.
Date: 1991-01-31
Client: LAMINATE IND. – PRESSED WOOD MANUFACTURER
Skills: Drawing board
Period Employed (start and finish) AUGUST 1990 – NOVEMBER 1990
Position: Draughtsman
List Projects:
Projects: Capture complete plant and equipment on block plan.
Duties and Responsibilities: Produce block plan.
Date: 1990-08-31
Client: MECO INTERNATIONAL – COAL MINING
Skills: Drawing board
Period Employed (start and finish) JULY 1990 – AUGUST 1990
Position: Draughtsman
List Projects:
Projects: Detailing long wall mining equipment.
Date: 1990-06-30
Client: BABCOCK – BOILERS & PLANT EQUIPMENT
Skills: Drawing board
Period Employed (start and finish) MARCH 1990 – JUNE 1990
Position: Draughtsman
List Projects:
Projects: SODA ASH BOTSWANA
Duties and Responsibilities: Detailing sluice water piping, boiler pressure parts and coal bunkers.
Date: 1990-03-31
Client: GENREC – STEEL STRUCTURES
Skills: Drawing board
Period Employed (start and finish) MARCH 1990
Position: Draughtsman
List Projects:
Projects: MOSGAS
Duties and Responsibilities: Structural detailing and creating templates for flame cutting.
Date: 1990-02-28
Client: HUMSA – SCREENS
Skills: Drawing board
Period Employed (start and finish) JANUARY 1990- FEBRUARY 1990
Position: Draughtsman
List Projects:
Projects: Non specific
Date: 1990-02-28
Client: HUMSA – SCREENS
Skills: Drawing board
Period Employed (start and finish) JANUARY 1990- FEBRUARY 1990
Position: Draughtsman
List Projects:
Projects: Non specific
Date: 1990-01-31
Client: INSULATIONS UNLIMITED – BUILDING INDUSTRY
Skills: Drawing board
Period Employed (start and finish) JUNE 1989 – JANUARY 1990
Position: Draughtsman
List Projects:
Projects: Factory upgrade – new drywall partitioning plant.
Duties and Responsibilities: Detailing new equipment for new product line.
Date: 1988-09-30
Client: ELOPTRO – ARMSCOR
Skills: Drawing board
Period Employed (start and finish) MAY 1984 – SEPTEMBER 1988
Position: Senior Draughtsman
List Projects: Optical field.
Projects: Classified
Duties and Responsibilities: Detailing optical equipment.
Date: 1988-09-30
Client: SCAW METALS – MINING. CAST PRODUCTS FOR MINING & RAILWAYS
Skills: Drawing board
Period Employed (start and finish) MAY 1984 – SEPTEMBER 1988
Position: Draughtsman
List Projects: Not a project house.
Duties and Responsibilities: Detail drawings, assembly drawings and plant layout drawings. Designing and drawing gauges for Inspection Department. Making customer drawings for the Sales Department. Casting drawings from machined samples, drawings for pattern making equipment and mould boxes. Layouts for new furnace installations.
Also some weight estimating of detail drawings to be used for pattern making purposes. Measure dragline equipment. Also responsible for all jig drawings for Machine Shop. Promoted to Machining Estimator and Jig and Tool Draughtsman. Design and draw all machining jigs. Also do machining estimating for outside customers plus in-house jobs ‑ writing job cards and planning sheets. Involved with General Management of Machine Shop. Attended N.C. Programming course.
Date: 1988-09-30
Client: JOY MINING MACHINERY – COAL MINING EQUIPMENT
Skills: Drawing board
Period Employed (start and finish) MAY 1982 – MAY 1984
Position: Draughtsman
List Projects: Not a project house.
Duties and Responsibilities: Tyred machine department. Responsible for shuttle cars, rock drills and coal cutters. Make new detail drawings. Redraw and metricate American drawings. Flame proofing drawings, hydraulic routing drawings, parts book drawings, and general arrangement drawings for catalogues. Mainly involved with new design improvements on shuttle cars. Visits to coal mines to observe mechanical problems in the field. Attended courses on maintenance of hydraulics and welding.
Date: 1982-05-31
Client: SCAW METALS – MINING. CAST PRODUCTS FOR MINING & RAILWAYS
Skills: Drawing board
Period Employed (start and finish) JANUARY 1978 – MAY 1982
Position: Apprentice fitter / Learner draughtsman
List Projects: Not a project house.
Duties and Responsibilities: Basic fitting techniques such as filing, shaping, chiselling shaft alignment, marking of procedures and basic gas plus arc welding.
Worked in plant under supervision of Maintenance Foreman. Fitting new bearings, replacing pump packings, stripping and overhauling machines. Site plus basic maintenance work. Detail drawing, redraw old drawings and various assembly drawings.